Work is under way on removing the bridge deck from the old eastbound I-44 bridge over 21st Street. The deck is being removed from southwest to northeast. Paving is nearing completion on 21st Street where the small detour and bridge pier were located. The bridge demolition will be completed in January 1990, at which time work will begin on building the new eastbound bridge. Photograph taken December 23, 1990.